Türkiye's Energy Regulator Reports 724 Accepted Distribution R&D Projects Since 2014 at the First Electricity Distribution Innovation Days in Ankara, 26-28 October 2026
Energy Minister Puts Transmission and Distribution Investment Under National Energy 2040 at About 100 Billion US Dollars; ELDER Gives Planned Distribution Spending of About 22 Billion Dollars Over Five Years; Mobile Leakage-Detection Project M.E.T.E. Ranked First Among 46 R&D Projects
Türkiye's Energy Market Regulatory Authority (EPDK) reported that 724 of 2,085 research and development project applications by electricity and natural gas distribution companies have been accepted since July 2014, 619 of them in electricity distribution and 105 in natural gas distribution. The figures were given at the 1st Innovation, Dissemination and Entrepreneurship Days in the Electricity Distribution Sector, organised by EPDK and the Association of Electricity Distribution Services (ELDER) in Ankara from 26 to 28 October 2026. The Minister of Energy and Natural Resources stated that about 100 billion US dollars of transmission and distribution investment is envisaged under National Energy 2040, due to be announced on 5 November 2026. ELDER put planned distribution investment and maintenance spending for 2026-2030 at about 22 billion dollars. The EPDK President described an amendment to the distribution R&D framework adopted by EPDK Board Decision No. 14846 of 3 September 2026 and published in the Official Gazette on 5 September 2026, and gave National Smart Meter System installations of about 4 million EKO-type and 70,000 PRO-type meters as of September. Forty-six projects competed in the 4th R&D Dissemination Summit, and the mobile leakage-detection project M.E.T.E. was ranked first by vote on 27 October.
Türkiye's Energy Market Regulatory Authority (EPDK) reported that 724 of 2,085 research and development project applications by electricity and natural gas distribution companies have been accepted since July 2014; 619 of the accepted projects are in electricity distribution and 105 in natural gas distribution. The figures were given by the EPDK President at the 1st Innovation, Dissemination and Entrepreneurship Days in the Electricity Distribution Sector, held in Ankara from 26 to 28 October 2026; press reports give the event's name in two variants. Reports describe the event as organised by EPDK and the Association of Electricity Distribution Services (ELDER); some state that EPDK supported the event and ELDER coordinated it. The Minister of Energy and Natural Resources, the EPDK President and the ELDER Chairman of the Board spoke at the opening on 26 October. The 4th R&D Dissemination Summit, held within the event, selected its winning project by vote on 27 October.
Minister: National Energy 2040 and grid investment
The Minister stated that about 100 billion US dollars of investment in electricity transmission and distribution infrastructure is envisaged under National Energy 2040 (Milli Enerji 2040), a strategy due to be announced in Istanbul on 5 November 2026. The figure covers transmission and distribution together; a split between the two was not reported. According to the Minister, the share of electricity in Türkiye's final energy consumption was 15 per cent in 2002 and 21 per cent at the time of the 26 October 2026 speech, with 30 per cent in industry and 33 per cent in buildings. He referred to a Global Electrification Pledge proposed for COP31, to be held in Antalya from 9 to 20 November 2026, under which electricity would account for 35 per cent of global final energy consumption by 2035. Electric vehicles, the electrification of industry, artificial intelligence and data centres were listed as demand drivers, and grid modernisation, digitalisation, domestic software and cyber security as agenda items. Hibya quoted the Minister as saying, in this publication's translation: 'In other words, the new era in electricity distribution will be an era of smarter, more flexible and more resilient grids as well as stronger grids.'
Regulator: amended R&D framework
The EPDK President described an amendment to the distribution R&D framework. The amendment was adopted by EPDK Board Decision No. 14846 of 3 September 2026 and published in Official Gazette No. 33361 of 5 September 2026; under its Article 1 it amends the Procedures and Principles on Supporting the Research, Development and Innovation Activities of Electricity and Natural Gas Distribution Companies published in Official Gazette No. 31089 of 4 April 2020. Those procedures were adopted by Board Decision No. 9268 of 26 March 2020; Article 18 of those procedures repealed Board Decision No. 5036 of 28 May 2014 (Official Gazette No. 29034, 18 June 2014). According to the President, pre-series prototype development, validation testing, pilot applications, field demonstrations, cyber security testing and localisation have been brought within the scope of support under specified conditions, provisions on the protection of intellectual and industrial property rights have been added, and incubation centre, accelerator programme, training and dissemination costs are supported under specified conditions. The Official Gazette text contains the following provisions. From 1 January 2027, R&D project applications are to be made each year in April and October, with decisions by the end of June and December respectively (Article 8(1)); under Article 12 of the amending procedures this provision enters into force on 1 January 2027 and the other provisions on the date of publication. Three groups of costs are met from the R&D budget up to 10 per cent of the company's R&D budget for the tariff period (Article 5(9)): costs of applications rejected at the application stage that the Board finds reasonable; costs of an R&D centre, design centre or incubation centre set up by the company, other than those met under other legislation; and, subject to paragraph 2 of Article 5, costs of supporting and encouraging entrepreneurship through incubation centres, accelerator programmes, idea competitions, training and dissemination workshops, national and international fairs and events and cooperation with technoparks, including related travel and accommodation. For each patent obtained from an R&D project approved by the Commission, 5 per cent of the approved project budget is added to the company's R&D budget, capped at 1,500,000 Turkish lira per project; the amount is indexed to the July 2026 consumer price index and updated by the index for the month in which the patent is obtained (Article 5(10)); the 2020 text of the procedures set the cap at 500,000 lira. An application for product development (Ür-Ge) is made within three months of the submission of the R&D project's final report; the Ür-Ge duration may not exceed 50 per cent of the initially approved R&D project duration and its budget 30 per cent of the initially approved R&D project budget, and at least 15 per cent of the R&D budget is to be allocated to Ür-Ge activities (Article 5(11) and (12)). Revenue from the licensing, sale, rental, transfer of usage rights or similar use of products, software, systems, equipment or technologies developed under R&D or Ür-Ge activities is taken into account in the company's tariff calculations; of this revenue, at least 10 per cent of the annual net turnover from software products and systems and at least 1 per cent of the annual net turnover from activities developing materials, equipment, devices, hardware or physical products are left to the distribution companies leading and partnering in the project (Article 11(4) and (5)). Under the Domestic Software Ecosystem Call, open since January 2023, 72 applications have been made and 26 accepted.
Fifth tariff period and smart metering
For the fifth implementation period, 2026 to 2030, the EPDK President stated that the investment ceiling has risen to about 1.5 times the previous period's level in real terms and the planned maintenance allocation to 2.1 times. This publication's Top Story of 26 June 2026 recorded the approved fifth-period capital expenditure ceiling as 18.5 billion dollars, 64 per cent above the 11.2 billion dollars of the fourth period; the 1.5 times figure is stated in real terms and the 64 per cent figure in US dollars. A quality factor regulation issued in April 2026 links outage, technical quality, customer satisfaction and occupational health and safety criteria to the revenue cap. The transition to the National Smart Meter System (MASS) began on 1 March 2026. As of September about 4 million EKO-type and 70,000 PRO-type meters had been installed, and about 2.7 million PRO-type meters are planned by the end of 2027. About 7 million subscribers are to be brought under remote reading by the end of 2027, and outage and technical quality data at the connection point are to be monitored for 15 million subscribers. The ELDER Chairman stated that consumers will not be charged for meter replacement under MASS.
Distribution sector figures given by ELDER
The ELDER Chairman put distribution investment in 2025 at more than 2.5 billion US dollars. About 22 billion dollars of investment and maintenance is expected for 2026-2030; according to the Anadolu Agency report of 28 October 2026, this comprises the investment ceiling of 18.5 billion dollars set for 2026-2030 together with planned maintenance resources. The investment need to the end of 2035 is given as at least 50 billion dollars. The loss and theft rate fell from 18.5 per cent in 2013 to 8.8 per cent in 2025; according to the same report, the ELDER Chairman stated that it had been calculated that without this improvement the sector's total cost would have been about 3 billion dollars higher. The sector comprises 21 distribution companies, more than 1.6 million km of lines and 52 million consumers. ELDER projects consumption rising from about 361 TWh in 2025 to 510 TWh in 2035, an increase of about 41 per cent; the 510 TWh value for 2035 matches the National Energy Plan projection cited in the IEA's Türkiye 2026 review. Spending on R&D dissemination was 332 million Turkish lira in 2025. The Enerjim Sensin entrepreneurship programme, run since 2019, has received 981 applications and supported 280 start-ups; these employ more than 1,400 people, 40 of them operate abroad, their combined turnover is 155 million dollars and they have raised 25 million dollars of investment. The 2026 round received 218 applications and selected 20 finalists.
4th R&D Dissemination Summit
Forty-six projects competed in the 4th R&D Dissemination Summit. On the votes of distribution companies and EPDK on 27 October, first place went to M.E.T.E. (Mobile Electricity Detection Equipment), led by ADM Elektrik Dağıtım with GDZ Elektrik Dağıtım and Osmangazi Elektrik Dağıtım as partners. According to Yeni Birlik, 28 October 2026, directional sensors integrated on a vehicle scan changes in the surrounding 50 Hz electric field while the vehicle is moving, detect leakage current and contact voltage risks on street lighting, manholes and metallic network components without physical contact, and transfer the data in real time to in-vehicle tablets and GPS-based digital maps; Net Haber (İhlas News Agency) describes vehicle-mounted sensors that measure while moving and transfer the data in real time to digital platforms. The award amount, project cost and detection accuracy were not published.
Watchpoints
The following items are stated as unmeasured or unreconciled. EPDK and ministry press releases on the event were not located, and EPDK's news page carried no announcement on the event as of 28 October 2026; speech figures are taken from the Anadolu Agency text carried by Dünya and from other Turkish outlets listed below. The EPDK President was reported as citing a 5 per cent increase in the weighted average cost of capital (WACC) for 2026-2030 for distribution companies using domestic software; the reports do not state whether the increase is in percentage points or relative. The 11.2 billion dollar figure for 2021-2025 is reported in two readings: Enerji Günlüğü and the Anadolu Agency report of 26 October 2026 give it as investment carried out over the past five years, while Habertürk reports that the companies exceeded an investment ceiling of 11.2 billion dollars for 2021-2025. This publication recorded 11.2 billion dollars as the capital expenditure of the fourth tariff period in its Top Story of 26 June 2026, and DHA reported ELDER's realised investment over the past five years as 12 billion dollars at the 25 June 2026 press conference. The 22 billion and 50 billion dollar figures cover different horizons, 2026-2030 and the period to the end of 2035. The 100 billion dollar figure is carried from the Minister's speech and refers to National Energy 2040; the National Energy 2040 document is due on 5 November 2026. On 22 September 2026 the Minister gave at least 30 billion dollars for the transmission network and at least 50 billion dollars for the distribution network to 2035, a total of 80 billion dollars, as recorded in this publication's Top Story of 30 September 2026; the 100 billion and 80 billion dollar figures refer to different horizons, 2040 and 2035.