Tashkent to Prepare a 15-Year Energy Programme for Afghanistan as the 800-1,000 MW Corridor Is Built
Uzbekistan to Prepare a 15-Year Energy Programme for Afghanistan: The 243-Million-Dollar Grid Package Advances, and CASA-1000's Afghan Section Remains the Last Unfinished Piece
At a meeting on 2 August, Afghanistan's national power utility DABS and Uzbekistan's first deputy energy minister agreed to set up joint technical working groups, and Uzbekistan announced it will prepare a comprehensive 15-year programme for Afghanistan's energy sector once feasibility studies are complete — a framework step, not a signing. It follows construction already under way: a four-contract package worth about 243 million dollars, signed in Kabul on 17 August 2025 between Uzbekistan's energy ministry and DABS, is building the 500-kilovolt Surkhan-Dasht-e-Alwan line and its substations to lift Afghanistan's import capacity from Uzbekistan to 800-1,000 megawatts, with the line targeted for 1 April 2027. On CASA-1000, the 1.2-billion-dollar Central-to-South Asia transmission project, the Kyrgyz section is complete and the Afghan section is the last unfinished piece — DABS puts it at about 80 per cent, while World Bank monitoring of physical works shows roughly a third of the towers standing. Afghanistan generates only about 250 megawatts of its own power and imports roughly 80 per cent of its electricity; Uzbekistan, its largest supplier since 2002, set an all-time daily consumption record of its own on 20 July.
On 2 August, DABS chief executive Mullah Abdul Haq Hamkar met Uzbekistan's First Deputy Energy Minister Umid Mohammadaminov — a name Uzbek sources also render as Mamadaminov — in a meeting that produced two concrete outcomes: joint technical working groups, and the announcement that Uzbekistan will prepare a comprehensive 15-year programme for the development of Afghanistan's energy sector after feasibility studies are completed, covering generation, transmission, distribution, engineering design, metering and studies for hydro, solar, gas and coal plants. No financing agreement was signed in August 2026; the framework builds on contracts concluded a year earlier and on construction already in progress.
The Package Under Construction
The reference point is the four-contract package signed in Kabul on 17 August 2025 between Uzbekistan's energy ministry and DABS — Da Afghanistan Breshna Sherkat — worth about 243 million dollars in most accounts; gazeta.uz puts the package at 250 million. It covers the 500-kilovolt Surkhan-Dasht-e-Alwan transmission line, called Surkhan-Puli-Khumri in Uzbek sources, with a capacity of 1,000 megawatts and 200.6 kilometres on Afghan territory plus 45 kilometres in Uzbekistan; the expansion of the Arghandi substation near Kabul by 800 MVA; a 220-kilovolt double-circuit line of 125 kilometres and 800 megawatts from Butkhak to Sheikh Mesri; and a new 126 MVA substation at Sheikh Mesri in Nangarhar. The contracts run on an 18-month schedule; field work began in September 2025, and the 500-kilovolt line is targeted for 1 April 2027. Uzbek officials describe the line's supply as 24 million kilowatt-hours a day, or 6 billion kilowatt-hours a year — the annual figure matching the ceiling of the 2019 ten-year framework agreement rather than the line's arithmetic maximum. Once the package is complete, Afghanistan's import capacity from Uzbekistan rises to 800-1,000 megawatts. A separate supply contract for 2026 was signed in November 2025 by the state trader Uzenergosotish and DABS, then led by Abdul Bari Omar.
Afghanistan's Supply Balance
Afghanistan generates about 250 megawatts domestically against roughly 800 megawatts of imports from Uzbekistan, Tajikistan, Turkmenistan and Iran; about 80 per cent of consumption is imported, at an annual cost of 250-280 million dollars, against a stated need of 6,000-7,000 megawatts. Uzbekistan has been the largest supplier since 2002. It delivered 2.6 billion kilowatt-hours in 2019 and 1.82 billion in 2023 for 91.2 million dollars — about five US cents per kilowatt-hour; its electricity export revenue for January-September 2025 reached 114.8 million dollars, about 1.5 times the prior year. The Jamestown Foundation reports that DABS paid 86.9 million dollars of accumulated arrears in May 2024. In July 2026 the Taliban leadership approved a five-year electricity development plan — 25 generation projects, 36 transmission projects, 42 substations and 34 distribution projects — and DABS announced 1,820 megawatts of generation contracts; costs and financing were not disclosed.
CASA-1000: Two Measures of the Last Section
The Kyrgyz section of CASA-1000 — the 1,387-kilometre, 1.2-billion-dollar line designed to carry 1,300 megawatts of summer hydro surplus from Kyrgyzstan and Tajikistan to Afghanistan and Pakistan — is complete, and the Tajik and Pakistani sections are largely built. The Afghan section, 582 kilometres in three phases with 1,713 towers, is the last unfinished piece, and its reported progress depends on the measure used. DABS has put the section at about 70 per cent in March 2025, 75 per cent in April 2026 and 80 per cent in May 2026 — figures that include delivered equipment. The World Bank's monitoring of physical works reads differently: about 18 per cent of the towers had been erected when work stopped in August 2021, and since the December 2024 resumption — financed on a ring-fenced basis from about 110 million dollars of uncommitted balances — 310 further towers, 79 foundations and 18.16 kilometres of conductor stringing were completed by December 2025, a cumulative total of roughly 36 per cent of the towers. Completion claims span end-2026, from Tajikistan's first deputy energy and water resources minister Jamshed Shoimzoda, with operation from January 2027, to late 2027 in the project's ESDF report. Afghan transit revenue estimates range from 40 to 65 million dollars a year.
Seasonal Profiles of the Two Systems
Uzbekistan's own system set records in the same weeks the export corridor advanced: daily consumption reached an all-time high of 301.9 million kilowatt-hours on 20 July 2026 — the first reading above 300 million, 10.75 per cent above the 2025 summer peak — with peak load at 14.2 gigawatts. Its generation has grown from 59 billion kilowatt-hours in 2016 to 81.5 billion in 2024, and the energy ministry has said exports can rise severalfold once the 500-kilovolt line is complete. CASA-1000 is built around the opposite season: it carries the summer surplus of the Kyrgyz and Tajik hydro systems. The watchpoints are specific — the 1 April 2027 target for the Surkhan line, the pace of tower erection on the Afghan CASA-1000 section, and whether the 15-year programme becomes a signed document.