A 371 Million Dollar Financing Plan from ADB, the World Bank and Counterpart Funds Covers the Renovation of 60 of 193 Substations at 35-110 kV Classified as Critical by Uzbekistan's National Electric Grid, 2026-2030

ADB Signed Its 200 Million Dollar Results-Based Loan in Bangkok on 15 October 2026; the World Bank Projects Database Shows 27 October 2026 as the Board Approval Date and 'Pipeline' as the Status of a 100 Million Dollar IBRD Loan; Seven Disbursement-Linked Indicators Include a Reduction in Calculated Technical Losses from 58,500 to 38,500 MWh a Year

UzEnergyNews · Top Story · ·Türkçe sürümü →

The Asian Development Bank (ADB) and the Government of Uzbekistan signed a 200 million US dollar results-based loan for the Modernization of Electricity Distribution Systems Program in Bangkok on 15 October 2026. The World Bank projects database lists 27 October 2026 as the Board approval date for a 100 million dollar IBRD loan to the same programme, shows the project status as 'Pipeline' and gives a total programme cost of 371 million dollars; according to the financing plan in ADB's Report and Recommendation of the President, the remaining 71 million dollars is financing from the Government of Uzbekistan and/or the implementing agency, JSC National Electric Grid of Uzbekistan (NEGU). The programme runs from 2026 to 2030 and provides for the renovation of 60 substations at 35-110 kV, to be selected from 193 that NEGU has identified as overloaded and without redundancy, and their digitalisation by 2030. Disbursement of the 300 million dollars of ADB and World Bank financing is linked to seven indicators verified by the state energy inspectorate Uzenergoinspeksiya, including a reduction in calculated technical losses in the renovated substations from 58,500 MWh a year to 38,500 MWh a year and in the share of transformers loaded at 90 per cent or more from 50 per cent to 20 per cent.

The Asian Development Bank (ADB) and the Government of Uzbekistan signed a 200 million US dollar results-based loan for the Modernization of Electricity Distribution Systems Program (ADB project number 58309-001) in Bangkok on 15 October 2026. The agreement was signed by the ADB President and by Uzbekistan's Deputy Prime Minister and Minister of Economy and Finance. The World Bank projects database lists 27 October 2026 as the Board approval date for a 100 million dollar loan from the International Bank for Reconstruction and Development (IBRD) to the same programme (World Bank project number P514733), shows the project status as 'Pipeline' (accessed 29 October 2026) and gives a total programme cost of 371 million dollars. The remaining 71 million dollars is listed in ADB's Report and Recommendation of the President (RRP) as financing from the Government of Uzbekistan and/or the implementing agency, Joint-Stock Company National Electric Grid of Uzbekistan (NEGU). The programme covers 2026 to 2030. ADB describes the operation as its first energy operation under the ADB–World Bank Full Mutual Reliance Framework and as the first results-based lending operation in Uzbekistan's energy sector.

Financing plan and loan terms

In the RRP financing plan, ADB ordinary capital resources account for 200.0 million dollars (53.9 per cent), IBRD for 100.0 million dollars (26.9 per cent) and the Government of Uzbekistan and/or NEGU for 71.0 million dollars (19.2 per cent). The programme is co-financed under the Full Mutual Reliance Framework (FMRF), with ADB as lead lender and the World Bank as trail lender, and ADB policies, procedures and implementation systems apply. The ADB loan has a 25-year term including a five-year grace period, an interest rate set under ADB's Flexible Loan Product, a commitment charge of 0.15 per cent a year, an average maturity of 15.25 years and a maturity premium of 0.10 per cent a year. The IBRD loan is expected to have a 25-year term including a five-year grace period under the IBRD Flexible Loan. The government is to relend the ADB loan proceeds to NEGU under a subsidiary loan agreement, with NEGU bearing the foreign exchange risk. The expenditure framework, in 2025 prices, allocates 227.5 million dollars (61.3 per cent) to equipment, 59.8 million dollars (16.1 per cent) to construction and installation, 55.0 million dollars (14.8 per cent) to taxes, 16.0 million dollars (4.3 per cent) to financing charges during implementation and 12.7 million dollars (3.4 per cent) to other costs. Climate finance is estimated at 206.6 million dollars, of which 162.0 million dollars is mitigation and 44.6 million dollars adaptation. An ADB technical assistance grant of 650,000 dollars accompanies the loan.

Scope: 60 substations at 35-110 kV

According to the RRP, NEGU has identified 193 of the 1,752 substations at 35-110 kV as constantly overloaded and lacking redundancy; the 60 programme substations are to be selected from these 193. Cabinet of Ministers Resolution No. 844 of 17 December 2024 provided for the transfer of all 35 kV and 110 kV infrastructure from Joint-Stock Company Regional Electrical Power Networks (REPN) to NEGU with effect from 1 June 2025; according to the program expenditure and financing assessment annexed to the RRP, all 35 kV and 110 kV assets except those in the Fergana and Bukhara regions were transferred to NEGU in 2025. NEGU is the executing agency for the programme. The programme finances part of a broader government programme of 5.0 billion dollars for 2025-2035, based on Cabinet of Ministers Resolution No. 599 of 22 September 2025, of which 1 billion dollars is listed as government funding and 4.0 billion dollars as funding from international financial institutions. Renovated transformation capacity in the programme substations is to reach 1,800 MVA by 2030, and all 60 substations are to be digitalised by 2030. A substation counts toward the digitalisation target only when commissioned with IEC 61850-based digital substation automation and advanced metering infrastructure of at least Type 2. Substations financed by other ADB, World Bank or development partner operations, and substations renovated before July 2025, are not eligible. ADB's program soundness assessment projects a reduction in energy losses of 20 to 30 per cent per substation and in operation and maintenance costs of about 50 per cent.

Disbursement-linked indicators and verification

Disbursement of the ADB and World Bank loans, 300 million dollars in total, is linked to seven disbursement-linked indicators. The two outcome indicators carry 40 per cent of the financing, the two physical output indicators 40 per cent and the three institutional indicators 20 per cent. Technical losses in the renovated substations are to fall from a baseline of 58,500 MWh a year in June 2025 to 38,500 MWh a year in 2030, a reduction of 20,000 MWh a year, and the share of transformers in the programme substations operating at 90 per cent of load or more is to fall from 50 per cent to 20 per cent. The verification protocol states that no metering system reliably measures total losses across a whole substation; losses are therefore calculated at transformer level from nameplate parameters, or from GOST standards for older transformers, and the average annual load, with an ageing factor of 10 per cent for transformers older than 20 years and 30 per cent for those older than 35 years. Achievement is verified by Uzenergoinspeksiya, the energy infrastructure inspectorate under the Cabinet of Ministers. The institutional indicators include ISO 9001, ISO 37001 and ISO 27001 certification, one additional independent board member, a risk management system based on the COSO 2004 framework, a first loan agreement with an international commercial lender, a NEGU credit rating at least equivalent to one notch below Uzbekistan's sovereign rating, and the training of at least 20 technical staff in smart grid technologies. Financing for prior results of up to 12 per cent and advance financing of up to 25 per cent of each loan are available, with a combined cap of 25 per cent. The combined disbursement schedule allocates 33.9 million dollars to prior results and 87.0, 73.5, 55.5 and 50.1 million dollars to 2027, 2028, 2029 and 2030 respectively. The design and monitoring framework also sets targets of at least 22,759 tonnes of CO2 equivalent avoided each year and at least 3.3 GW of renewable energy capacity enabled with indirect support; the 3.3 GW is to be considered achieved on completion of the network investments, regardless of the commissioning status of the associated generation.

Sector figures cited in the RRP

The RRP gives Uzbekistan's electricity demand as 86.7 TWh in 2025, growing at about 5 per cent a year, and the maximum load as having risen from 10.4 GW in February 2019 to 13.3 GW in July 2025, with thermal power plants operating at up to 93 per cent of capacity. About 8 GW of wind and solar capacity has been installed since 2021, including about 2 GW of rooftop solar, equal to 36 per cent of installed generation capacity according to IRENA statistics cited in the RRP. Distribution technical losses are estimated at 14 per cent, and most of the distribution network and substations have been in operation for more than three decades. About 80 per cent of electricity generated in 2025 came from fossil fuels, and the government's renewable energy capacity target is 25 GW by 2030.

Earlier distribution operations

The programme is separate from two earlier distribution operations for which REPN was named as the implementing or executing agency at approval. World Bank project P504630, Electricity Distribution Improvement and Strengthening through Commercialization and Transformation, is a Program-for-Results operation covering a 150 million dollar programme, of which 100 million dollars is financed by the International Development Association, for 10, 6 and 0.4 kV networks in high-priority regions including Surkhandarya region and the Republic of Karakalpakstan; its appraisal document is dated 23 April 2025 and the World Bank approved it on 15 May 2025. ADB project 56231-001, the Distribution Network Digital Transformation and Resiliency Project, is an investment project with a cost of 352.2 million dollars, including a 200 million dollar ADB loan, co-financing from Agence Française de Développement and 77.2 million dollars of counterpart funding, for the modernisation and digitalisation of 26 substations at 35 kV and 110 kV; its RRP is dated August 2023. Under the eligibility rule of the new programme, substations financed by these or other development partner operations cannot be counted toward its indicators.

Watchpoints

The following items are stated as unconfirmed or unreconciled. The World Bank projects database lists 27 October 2026 as the Board approval date for P514733, with a commitment of 100 million dollars and a total project cost of 371 million dollars, and shows the project status as 'Pipeline' (accessed 29 October 2026); a World Bank press release on the approval had not been located as of 29 October 2026. ADB's news release of 15 October 2026 stated that World Bank management was expected to seek Board approval later that month. The ADB Board approval date does not appear in the documents consulted for this account, which uses the signing date. The financing plan attributes the 71 million dollar counterpart contribution to the Government of Uzbekistan and/or NEGU without giving a split between the two. Outcome targets in the design and monitoring framework are dated 2031, while the programme period and output targets end in 2030. ADB describes the programme as the first results-based lending operation in Uzbekistan's energy sector; the appraisal document of World Bank P504630, a Program-for-Results operation approved on 15 May 2025, describes that operation as the first Program-for-Results in the country.

Sources: Asian Development Bank, Report and Recommendation of the President to the Board of Directors, Proposed Results-Based Loan and Technical Assistance Grant, Republic of Uzbekistan: Modernization of Electricity Distribution Systems Program (Cofinanced Under the Full Mutual Reliance Framework), Project Number 58309-001, September 2026, paras 2, 5-6, 8-10, 21-22, 24-28, 30-31 and 34, Tables 1-4 and design and monitoring framework, World Bank Program Appraisal Document version dated 30 September 2026, disclosed 27 October 2026 (documents.worldbank.org, 099100626115027680); Annex 1, Disbursement-Linked Indicators, Verification Protocols, and Disbursement Schedule, Tables 1-3; Annex 3(i), Program Soundness Assessment, paras 9, 11 and 18; Annex 3(iv), Program Expenditure and Financing Assessment, para 8. ADB news release, Bangkok, 15 October 2026. World Bank projects database, P514733, accessed 29 October 2026. World Bank, Program Appraisal Document, Electricity Distribution Improvement and Strengthening through Commercialization and Transformation (P504630), 23 April 2025, and Implementation Status and Results Report No. 3. Asian Development Bank, Report and Recommendation of the President, Distribution Network Digital Transformation and Resiliency Project, Project Number 56231-001, August 2023. Analysis: UzEnergyNews.