The Regulator Takes the Ministry: Uzbekistan Replaces Its Energy Leadership

Uzbekistan Replaces Its Energy Minister and Grid Chief as the President Declares the Problem Is Management, Not Money

UzEnergyNews · Top Story · ·Türkçe sürümü →

By presidential decree on 27 July 2026, following a video conference on the fuel and energy sector, Uzbekistan dismissed Energy Minister Jurabek Mirzamakhmudov after nearly four years in office and appointed Sherzod Khodjaev, head of the electricity market regulator EMDRA since its creation, in his place. The chairman of Hududiy Elektr Tarmoqlari, the state distribution company serving 8.3 million customers, was replaced on the same day, the head of the energy inspectorate was confirmed, and the chief executives of four state energy companies were placed on probation until the end of the year. The stated grounds were serious shortcomings in the sector: first-half grid losses of 17.2 percent, about 4,000 outages in June and July alone, and interruptions reaching eight to ten hours. The president's formulation was categorical — the problem in energy is not money but the management of the system. The appointment leaves the regulator without a named director five weeks before the deadline for setting the parameters of the new asset-based tariff methodology.

By presidential decree on 27 July 2026, following a video conference chaired by President Shavkat Mirziyoyev on the priorities of the fuel and energy sector, Uzbekistan dismissed Energy Minister Jurabek Mirzamakhmudov and appointed Sherzod Khodjaev, director of the Energy Market Development and Regulation Agency, in his place. The official grounds, as reported by Gazeta.uz and Interfax, were serious shortcomings in the work of the sector. Mirzamakhmudov had held the post for nearly four years, appointed in September 2022 as deputy prime minister for the fuel, energy and chemical industries after leading the state nuclear agency. The change did not stop at the ministry. On the same day the chairman of Hududiy Elektr Tarmoqlari, the state joint-stock company that distributes electricity across the country, was dismissed on the same grounds and replaced by Sardor Isakulov; Akhad Isokjonov was confirmed as head of the state energy inspectorate; and the chief executives of four state energy companies, covering the national transmission grid, thermal generation, gas transport and regional gas supply, were placed on probation until the end of the year with an explicit warning that they too would be removed if results did not follow.

The numbers behind the dismissals

The president's case was quantitative. In the first half of 2026, losses in Uzbekistan's electricity networks reached 17.2 percent, or 4.8 billion kilowatt-hours, against an assessment of about 14 percent for 2024; natural gas losses stood at 7.6 percent, or 797 million cubic metres. Earlier official reporting had placed electricity losses above 20 percent in 44 districts. In June and July alone the system recorded roughly 4,000 outages, with interruptions in some areas lasting eight to ten hours, and more than 530,000 meters, around 300,000 for gas and 234,000 for electricity, were not transmitting data to automated systems. The argument that money is not the constraint was also quantitative: some 30 trillion soums have been spent on network modernisation in recent years, six times the total of the previous twenty-five years; roughly 23 billion dollars of foreign investment has entered the sector over a decade; 9.5 gigawatts of new capacity has been commissioned. Labour productivity in the sector nonetheless runs 1.5 to 2 times below international peers, and fault repair takes three to four times longer. The president put the infrastructure requirement for the coming decade at 8 billion dollars, which sharpens rather than softens the management question: capital on that scale is difficult to defend while a fifth of the electricity entering the network fails to reach a paying customer.

The regulator moves to the ministry and leaves an empty chair

Khodjaev's appointment carries a distinct institutional signal. He has worked in the sector since 1998, served as deputy energy minister from 2019, and was dismissed from that post in January 2023, during the winter supply crisis that became the previous low point of public confidence in the system. He returned a month later to head the ministry's project office for power sector reform, and from October 2023 built and led the Energy Market Development and Regulation Agency, the body created to regulate the electricity market as Uzbekistan moves from a single-buyer model toward competitive trading and cost-reflective network tariffs. The reformer dismissed in one crisis has been recalled to run the ministry in the next. His promotion, however, opens a gap precisely where the reform calendar is tightest. The agency's official leadership page listed no director as of 28 July, and no successor had been announced. Under the framework published by the Ministry of Economy and Finance, the parameters of the new tariff methodology based on a regulated asset base are to be set by 1 September 2026, with regulatory periods extending in stages from one year to five and indicative 2026 adjustments of about 9 percent in generation, 30 percent in transmission and 10 percent in distribution. Who signs those parameters, and with what degree of independence from a ministry now led by the regulator's founding director, is the open question of the next five weeks.

An operator for the wires

The distribution company changed hands with a different logic. Hududiy Elektr Tarmoqlari operates the low and medium-voltage networks that serve 8.3 million customers through fourteen regional units, with some 293,000 kilometres of lines, 97,000 transformer points, around 25,000 employees and 64.8 billion kilowatt-hours of useful supply in 2024. Its outgoing chairman, Asrorjon Askarov, had led the company only since December 2024. The incoming chairman, Sardor Isakulov, is thirty-nine and returns to the sector from regional government: he began as an electrician in the trunk transmission networks in 2006, held posts in the energy ministry, rose to first deputy chairman of the state thermal generation company, and then served as a district governor in Tashkent region from 2024. His first public statement set the register of the mandate, describing an instruction from the president to rebuild the system from zero. The appointment pattern is consistent: an operator with field experience for the wires, a market-builder for the ministry, an inspectorate confirmed the same day, and probation rather than confirmation for the four incumbent chief executives above them.

What the new team inherits

The in-tray is defined by three facts already on the public record. First, demand is at an all-time high: on 20 July the system delivered 301.9 million kilowatt-hours in a single day, crossing the 300-million threshold for the first time, with peak load at 14.2 gigawatts, after six consecutive daily records in one week of extreme heat. The loss percentages the president cited are levied on record volumes. Second, the tariff reform deadline of 1 September arrives with the regulator unstaffed at the top, and the July meeting's broader instruction, an accelerated transition to market mechanisms beginning with liquefied gas supply and a presidential decree to be drafted within three months, presumes a functioning regulatory counterpart. Third, the nuclear programme continues against an uncertain financing backdrop: first concrete was poured at the Jizzakh plant in early June, and while Rosatom's reported halving of its investment programme has produced no official Uzbek assessment of impact, a joint expert working group convened in Moscow on 22 and 23 July signals that both sides are managing the process rather than pausing it. The management instruments announced alongside the dismissals, a digitalisation and artificial intelligence centre to stress-audit the sector, ten performance indicators for 106,000 energy workers, artificial-intelligence analysis of automated metering data, and a model district in Yangiyul where the new minister personally chairs the crisis staff with a 1 October target, will be measurable against the same numbers that ended the last team's tenure: the loss percentage and the length of an outage. Winter will provide the test.

Sources: Presidential decree and appointments as reported by Gazeta.uz (27 July 2026, EN/RU/UZ editions), Spot.uz (27-28 July 2026) and Interfax (27 July 2026); loss figures from the presidential statement of 21 July 2026 as reported by Gazeta.uz; Hududiy Elektr Tarmoqlari company data from het.uz (as of 1 January 2025); biography of Sherzod Khodjaev from Gazeta.uz; biography of Sardor Isakulov from Kun.uz and Podrobno.uz (April 2024) and Spot.uz (27 July 2026); RAB tariff methodology framework from the Ministry of Economy and Finance via gov.uz (April 2026), UzDaily and Daryo (May 2026); demand record from the Ministry of Energy via Kun.uz and Spot.uz (20-21 July 2026); Jizzakh first concrete from World Nuclear News (June 2026); Rosatom investment programme as reported by Oilprice and Eurasianet (20 July 2026); Moscow joint working group from Spot.uz (26 July 2026). Copyrighted material is not reproduced. Analysis by UzEnergyNews.