Four Countries Lost Power on 14 August — and Bishkek and Astana Dispute What Caused It

Central Asia's Four-Country Blackout: A 600 MW Trip at Toktogul, About 2,810 MW of Curtailment in Kazakhstan, a Three-Hour Backbone Restoration — and Two Operators with Two Accounts of Causation

UzEnergyNews · Top Story · ·Türkçe sürümü →

On the afternoon of 14 August, two generating units at Kyrgyzstan's Toktogul hydropower plant — about 600 MW — disconnected at 14:37 Kazakhstan time, and within roughly forty minutes outages had reached four countries. Kazakhstan's grid operator KEGOC reports that protection opened three 500-kilovolt lines and the southern zone separated from the national grid, with consumer curtailment of about 2,810 MW across eight regions plus Almaty and Shymkent; districts of Bishkek and two Kyrgyz regions, cities and districts across Tajikistan, and Uzbekistan's Surkhandarya region also lost supply. Transmission was restored in about three hours in Kazakhstan and about five in Surkhandarya. Both operators confirm the trip; they dispute what it caused. KEGOC's account runs from the lost 600 MW to an overloaded north-south transit; Kyrgyzstan's energy ministry replies that frequency was back at 50 Hz within eighteen minutes and that the Almaty node went dark after that. A special commission is at work and no joint findings have been published — in January 2022, after a comparable four-country collapse, an interstate commission needed about seven weeks to publish an agreed cause. Uzbekistan's operator reports that staged emergency automation and battery storage kept its system from a frequency collapse.

At 14:37 Kazakhstan time on 14 August — all times here are Kazakhstan time, UTC+5; Kyrgyz statements, issued on UTC+6, are converted — two hydro units at Toktogul, the plant that produces about 40 per cent of Kyrgyzstan's electricity, disconnected on emergency protection. Both countries' operators confirm the trip. About 600 MW left the Central Asian unified energy system. KEGOC, Kazakhstan's transmission operator, reports that the north-south transit corridor overloaded and that emergency automation opened three 500-kilovolt lines — two Agadyr-Ulken circuits and Aktogay-Taldykorgan — separating the country's southern zone; its curtailment figure is approximately 2,810 MW, across eight regions and the cities of Almaty and Shymkent. Within roughly forty minutes, outages had been reported in districts of Bishkek, Chuy and Issyk-Kul in Kyrgyzstan; in Dushanbe, Khujand, Kulob, Vahdat, Norak, Hisor and other cities and districts in Tajikistan; and in Uzbekistan's Surkhandarya region.

The Sequence, in Kazakhstan Time

14:34 is the moment NESK, the Kyrgyz transmission operator, later identified as an external disconnection on the Kazakh north-south line, after which the Kyrgyz grid switched to isolated operation; its statement was published that afternoon, at around 17:10. At 14:37 the Toktogul units tripped — the minute the Kyrgyz ministry's 17 August statement confirms as the initial disturbance. Between 14:37 and 14:38, protection opened the three 500-kilovolt lines; the Almaty distributor Alatau Zharyq gives 14:38. At 14:38 Uzbekistan's energy ministry registered the disturbance reaching its system. Automatic load shedding cut about 300 MW at the Almaty node — four city districts and ten districts of Almaty region, a fraction of the national curtailment. At 14:47 the first 295 MW of curtailment was lifted in Karaganda, Ulytau and Abay; at 14:55 system frequency was back at 50 Hz (Kyrgyz ministry). At 15:11 the Almaty metro lost external supply and stopped, with passengers evacuated; traffic lights went dark, the airport ran on generators and hospitals switched to backup. Between 16:12 and 16:34 voltage returned to the Almaty node, the southern zone resumed parallel operation with the Central Asian system at 16:26, and Zhambyl, Turkistan and Kyzylorda were fully restored. At 17:40 KEGOC declared its transmission network fully restored, with distribution reconnections continuing into the evening; Surkhandarya was fully restored at 19:40, about five hours after the disturbance, and Kyrgyzstan and Tajikistan declared full restoration the same evening.

Two Operators, Two Accounts

Each account has its own timeline of disclosure. KEGOC's bulletin on 14 August did not name Toktogul: it attributed the event to a sudden change in power flows from the Central Asian unified system. The plant was named on 15 August by KEGOC's system services director Nurzhan Kerimkulov, in what is now Kazakhstan's position: 600 MW lost at Toktogul, the north-south transit overloaded, protection acted — a mechanism that is itself a single operator's account, not independently confirmed. On the Kyrgyz side, NESK's first statement cited an external disconnection on the Kazakh line and said no subscribers were disconnected — while Bishkek residents were reporting outages. The energy ministry's fuller reply came on 17 August: the Toktogul trip was the initial disturbance, but calling it the direct cause of neighbouring countries' outages is, in the ministry's word, incorrect — frequency was back at 50 Hz within eighteen minutes, the Almaty node went dark after that, and each country's internal protection performance should be examined separately. The ministry also states that the isolated Kyrgyz system remained stable and delivered about 250 MW to the grid, a claim not independently confirmed. A third timestamp — Alatau Zharyq's 14:38 for the line openings — does not fully align with either account, a point the Times of Central Asia has noted. A special commission was formed on 15 August; as of 20 August, no joint findings have been published, no public Kazakh response to the 17 August statement has appeared, and no statement has been found from the coordinating dispatch centre Energiya in Tashkent. One technical question is open on the record: 600 MW matches the tripped units' pre-modernisation rating of 300 MW each, but Toktogul's four units were uprated to 360 MW each by November 2025 — the figure may equally reflect measured output at the moment of the trip, and which units tripped, at what output, has not been stated.

One System, Built as a Ring

The Central Asian unified energy system was built in the 1960s and 1970s as a ring, balancing upstream hydro in Kyrgyzstan and Tajikistan against downstream thermal generation, and it is coordinated from the dispatch centre Energiya in Tashkent. Turkmenistan left the ring in 2003. Tajikistan was disconnected for fifteen years; its south and south-west rejoined in June 2024, with the northern zone's integration running through the first half of 2026. Kazakhstan's internal balance adds a second asymmetry: in 2024 its northern zone produced 73.3 per cent of national generation and the southern zone 13.2 per cent (Samruk-Energy), which is why the south depends on the north-south transit whose protection acted on 14 August. The system's largest precedent ran in the opposite direction. On 25 January 2022, a short circuit on the disconnector of a 500-kilovolt line at Uzbekistan's Syrdarya thermal plant took more than 1,500 MW offline at 11:59; the Kazakh north-south line tripped on the imbalance, Uzbekistan lost about 9,600 MW and Kyrgyzstan about 2,600 MW, and Tashkent, Almaty and Bishkek went dark together. That episode also produced the institutional mechanism now being tested: an interstate commission of the Kazakh, Uzbek and Kyrgyz system operators, convened under the dispatch centre Energiya, published its agreed conclusion in March 2022 — about seven weeks after the event — attributing the start of the collapse to outages in Uzbekistan's power system.

Uzbekistan's Report, and the Investment Programmes on the Table

Uzbekistan's transmission operator reports that staged emergency automation and battery storage prevented a frequency collapse and a cascading spread: the country avoided a wider blackout, with the deepest impact in Surkhandarya. The disturbance arrived in a season of records. On 17 July, the emergency disconnection of two 220-kilovolt lines — Kara-Balta-Glavnaya and Glavnaya-Chu — triggered automatic load shedding that cut power to most of Bishkek and almost all of Chuy region, with effects reported in Naryn, Talas and Osh; on 20 July, Uzbekistan set its all-time daily consumption record of 301.9 million kWh after six record days in a single week. The investment figures on the table predate the blackout: KEGOC announced a southern-zone reinforcement programme of 137.6 billion tenge in June (as reported by aNews); the Eurasian Development Bank puts the region's new capacity requirement at 62.8 GW by 2035, against demand growth of about 40 per cent by 2030; and the World Bank's REMIT programme, approved in January 2026, targets at least 15 billion kWh a year of cross-border trade — with the dispatch centre Energiya among the recipients of its first phase. Watchpoints: the special commission's findings, and whether the 2022 sequence — an agreed, published account of causation within weeks — repeats; any statement from Energiya; and clarification of the tripped units' output.

Sources: KEGOC press release of 14 August 2026 and statements by system services director Nurzhan Kerimkulov (15 August) via economist.kg; NESK statement of 14 August and the Kyrgyz Ministry of Energy statement of 17 August via economist.kg and Kazakhstan Today; Kazakh Ministry of Energy curtailment figure via TASS; Alatau Zharyq and the restoration timeline via Ulysmedia and Tengrinews; Uzbekistan's Ministry of Energy via gazeta.uz, spot.uz and kun.uz (14 August); Tajik Ministry of Energy via Asia-Plus and Sputnik Tajikistan; Times of Central Asia on the conflicting accounts; the January 2022 precedent and the March 2022 interstate commission conclusion via Interfax, The Diplomat, Eurasianet, spot.uz and KEGOC; CAPS structure via CAREC programme documentation; Toktogul modernisation via Times of Central Asia and POWER Magazine; investment figures via aNews (KEGOC), the Eurasian Development Bank and the World Bank (REMIT, 22 January 2026). Copyrighted material is not reproduced. Analysis by UzEnergyNews.