A Soviet-era unified ring, dismantled after Turkmenistan (2003) and Uzbekistan (2009) left it, is being rebuilt — not as a command system run from one control room, but as a traded regional market. The World Bank's REMIT program commits $1.018 billion to more than triple cross-border transfer capacity to 16 GW and lift electricity trade to at least 15,000 GWh a year.

After the Soviet Union collapsed, Central Asia inherited one of the most integrated power grids in the world: a single 500-kilovolt ring connecting Kazakhstan, Uzbekistan, Kyrgyzstan, Tajikistan and Turkmenistan, balanced from one dispatch centre in Tashkent. Within two decades the region had taken it apart. It is now rebuilding it — but with a different logic. The aim is no longer a command system run from a single control room, but a market in which neighbouring countries trade electricity across borders.

The instrument is the Regional Electricity Market Interconnectivity and Trade program, known as REMIT, approved by the World Bank on 22 January 2026. It is a ten-year, $1.018 billion program structured in three phases, intended to create Central Asia's first genuine regional electricity market — the first tranche of an estimated $5.5 billion in cross-border investment the region will need by the mid-2030s.

From One Ring to Five Grids

The Central Asian Power System was a Soviet design. A central dispatcher — the Coordinating Dispatch Centre 'Energia' in Tashkent — balanced flows across the entire region, allowing mountain hydropower and lowland thermal plants to cover each other's shortfalls. After independence the central dispatcher lost its authority and each state rebuilt its grid along national lines. Turkmenistan left the unified system in 2003 and Uzbekistan followed in 2009. Because the ring passed through Uzbek territory, Tajikistan was cut off from the system altogether when Uzbekistan withdrew.

The price of fragmentation became visible in January 2022, when a single fault cascaded into a region-wide blackout that left tens of millions of people across Uzbekistan, Kazakhstan and Kyrgyzstan without power. Most of the surviving cross-border lines dated from the 1970s and 1980s and had never been modernised. Re-integration, begun in 2018 at the initiative of Uzbek President Shavkat Mirziyoyev, gained new urgency.

What REMIT Funds

REMIT's first phase commits $143.2 million — $140 million in concessional financing from the International Development Association plus $3.2 million in CAWEP grants — to Kyrgyzstan, Tajikistan, Uzbekistan and CDC Energia, the regional dispatch centre that will operate the market. National transmission companies will carry out the physical grid investments while CDC Energia builds the market rules and institutions. The first phase alone is expected to enable roughly 900 MW of clean energy and to leverage about $700 million in private investment.

The Targets

Over the next decade the program aims to more than triple cross-border transfer capacity to 16 GW, lift annual electricity trade to at least 15,000 GWh and enable up to 9 GW of new clean-energy capacity. Cross-border trade currently meets only about 3 percent of the region's electricity demand, and existing interconnections run at less than half their capacity. The World Bank projects up to $15 billion in economic benefits by 2050, together with fewer outages, electricity prices roughly 10 percent lower, and emissions about 25 percent lower.

Complementary by Nature

The economic case rests on geography. Kyrgyzstan and Tajikistan hold large hydropower potential; Kazakhstan has the region's strongest wind resources; Uzbekistan is building solar at scale; Turkmenistan has gas. Because these resources peak in different seasons, a shared market lets hydro-rich neighbours sell surplus summer power and buy thermal or solar generation in winter. The same logic underpins a trilateral water-and-energy agreement signed by Kazakhstan, Kyrgyzstan and Uzbekistan in September 2025, under which Kyrgyzstan releases water from the Toktogul reservoir to its downstream neighbours in return for electricity. Two large projects anchor the coming phase: the roughly 2,000 MW Kambarata-1 hydropower plant on the Naryn river, developed jointly by Kazakhstan, Kyrgyzstan and Uzbekistan, and Tajikistan's Rogun plant, whose output will need an export corridor.

Why It Matters

For UzEnergyNews, the notable detail is where the market's centre sits. The institution that will run it, CDC Energia, is in Tashkent — the same control room that once balanced the Soviet ring. Uzbekistan's assigned role in the program is solar generation and regional connections, which places it at the centre of both the physical grid and the emerging market. Regional demand could nearly triple by 2050, beyond what any single country can meet on its own; that is the structural reason the region is rebuilding what it once dismantled.

The plan is not yet complete. Turkmenistan, whose 2003 exit began the fragmentation, is expected to join but has not formally done so, and Kazakhstan participates on its own terms. The $1.018 billion committed is only a first instalment against the roughly $5.5 billion the region will need, and a working market also requires harmonised rules, tariffs and dispute mechanisms — which take longer to build than transmission lines. The infrastructure is the easier half; the institution is the test.

Sources: World Bank (REMIT program press release, 22 January 2026; Charles Cormier; Maksudjon Safarov); Gazeta.uz; CDC Energia; Eurasianet; bne IntelliNews; The Diplomat; Times of Central Asia.