US Nuclear Regulatory Commission Issues Construction Permit for a BWRX-300 at the Tennessee Valley Authority's Clinch River Site, Described by the Agency as the First US Commercial Small Modular Reactor
Permit CPAR-2 Is Dated 28 September 2026 and Was Announced on 29 September After a 14-Month Review; It Sets 1 October 2031 and 30 September 2032 as the Earliest and Latest Construction Completion Dates, and Operation Requires a Separate Licence
The US Nuclear Regulatory Commission (NRC) issued Construction Permit No. CPAR-2 to the Tennessee Valley Authority (TVA) for Clinch River Nuclear Unit 1, a 300 MW GE Vernova Hitachi BWRX-300 boiling-water reactor at Oak Ridge in Roane County, Tennessee. The permit is dated 28 September 2026. The NRC announced it on 29 September and described the plant as the nation's first commercial small modular reactor. The NRC accepted the application on 9 July 2025 and states that its review took 14 months; the agency's stated target for construction permit decisions is 18 months. The permit sets 1 October 2031 as the earliest and 30 September 2032 as the latest date for completion of construction, and fuel loading requires a separate operating licence. The NRC described the decision as its second major reactor approval of 2026 without naming the first; the American Nuclear Society lists Construction Permit No. CPAR-1, issued on 9 March 2026 for Kemmerer Power Station Unit 1 in Wyoming, as the earlier permit. As of 30 September 2026, TVA had not announced a construction start date.
The US Nuclear Regulatory Commission (NRC) has issued Construction Permit No. CPAR-2 to the Tennessee Valley Authority (TVA), the federally owned US power utility, for Clinch River Nuclear Unit 1 in Roane County, Tennessee. The permit, issued under Docket No. 50-615, carries a date of issuance of 28 September 2026. The NRC announced the decision on 29 September 2026 in press release No. 26-079, which describes the plant as the nation's first commercial small modular reactor. TVA plans to build a 300 MW GE Vernova Hitachi BWRX-300 boiling-water reactor at its Clinch River site in Oak Ridge. The application references Early Site Permit No. ESP-006, which the NRC issued for the site in 2019. The construction permit does not authorise operation. According to the NRC release, TVA will need a separate operating licence from the NRC before loading fuel and starting operations.
Terms of the permit
The permit sets 1 October 2031 as the earliest and 30 September 2032 as the latest date for completion of construction, and it expires on the latest completion date. Paragraph 3 of the permit makes it subject to the conditions for construction permits in section 50.55 of Title 10 of the Code of Federal Regulations and lists seven further conditions, 3.A to 3.G. Conditions 3.A to 3.C set the completion dates, the site in Roane County and the scope of the authorised construction. Under condition 3.D, TVA is to carry out detailed geologic mapping of the excavations for safety-related structures, examine and evaluate the geologic features found in those excavations, and notify the NRC when the mapping information is available for examination. Under condition 3.E, an applicant for a combined licence or an operating licence that references the permit and has determined that an offsite emergency planning zone is required must update the evacuation time estimate; a footnote to the permit states that this condition was originally identified in the early site permit. Condition 3.F requires reactor isolation valve bodies to undergo a one-time augmented volumetric examination during construction and before initial start-up, using the procedures and acceptance criteria of section III, paragraph NB-2540, of the American Society of Mechanical Engineers code. Condition 3.G incorporates a non-radiological Environmental Protection Plan, which requires TVA to adhere to the incidental take statement of a Biological Opinion issued by the US Fish and Wildlife Service. The Biological Opinion concludes that construction and operation are not likely to jeopardise the continued existence of certain species, including the Indiana bat, the northern long-eared bat, the gray bat and the tricolored bat.
Under paragraph 4 of the permit, the NRC will not issue a licence to operate the facility unless four requirements are met: TVA submits the complete final safety analysis report; the Commission finds that the final design provides reasonable assurance that operation will not endanger public health and safety; the Commission finds that operation will be in accordance with its environmental protection regulations in Part 51 of Title 10 of the Code of Federal Regulations; and TVA submits proof of financial protection and executes an indemnity agreement under section 170 of the Atomic Energy Act. Among its findings, the permit records that TVA has not identified any safety features or components that require research and development.
Review schedule: planned and actual dates
TVA submitted the application in two parts: an environmental report in April 2025 and a preliminary safety analysis report on 20 May 2025. The NRC staff accepted the application for detailed review by letter of 9 July 2025, and the notice of acceptance for docketing was published in the Federal Register on 15 July 2025. In a schedule letter of 25 July 2025, the staff estimated that the safety and environmental reviews would require approximately 25,000 staff hours and 1.4 million dollars in contractor support, with hearing activities excluded from the estimate. The letter states that the schedule does not include the hearing process, and it gives no date for a permit decision.
The NRC project page records the following completion dates against the target months in the letter of 25 July 2025. The draft safety evaluation, targeted for February 2026, was completed on 16 January 2026. The draft supplemental environmental impact statement, targeted for December 2025, was issued on 7 November 2025, and the final statement, targeted for April 2026, on 6 April 2026. The advance safety evaluation report, targeted for October 2026, was completed on 29 May 2026. In a letter of 18 June 2026 (accession no. ML26160A308), the staff moved the target for the final safety evaluation from November 2026 to 30 June 2026 and gave an estimate of approximately 16,500 staff hours and 1.4 million dollars in contractor support for completing the review and issuing the permit; the letter of 25 July 2025 had estimated 25,000 staff hours and 1.4 million dollars for the safety and environmental reviews, excluding the hearing. The final safety evaluation report was completed on 25 June 2026.
The mandatory hearing was held in Oak Ridge on 13 August 2026. In press release No. 26-075 of 5 August 2026, the NRC stated that the hearing marked the first time the agency had used its modernised mandatory hearing framework for an advanced reactor licensing review. The project page lists 28 August 2026 for post-hearing comments and 28 September 2026 for the permit decision. The 29 September release states that the NRC formally began its review in July 2025 and completed its licensing decision in 14 months; the period from the acceptance letter of 9 July 2025 to the permit date of 28 September 2026 is 14 months and 19 days. The NRC Chairman said in the release: "Four months ahead of schedule is what the new NRC looks like."
Federal review timelines and the first permit of 2026
Executive Order 14300 of 23 May 2025 directs the NRC to set a deadline of no more than 18 months for a final decision on an application to construct and operate a new reactor of any type, commencing with the first required step in the regulatory process. In its release of 5 August 2026, the NRC stated that it targets construction permit decisions within 18 months as part of its modernisation initiative.
The 29 September release describes the Clinch River decision as "the agency's second major reactor approval this year" and does not name the first. Construction Permit No. CPAR-1 was issued on 9 March 2026 to US SFR Owner, a subsidiary of TerraPower, for Kemmerer Power Station Unit 1 in Lincoln County, Wyoming, following a Commission decision of 4 March 2026 (CLI-26-5). TerraPower filed that application in March 2024, and the NRC staff accepted it and began the formal review in May 2024. In its release of 4 March 2026, the NRC described Kemmerer as the first commercial reactor it had approved for construction in nearly a decade and its first approval for a non-light-water reactor in more than 40 years. The Kemmerer plant is a 345 MWe sodium-cooled reactor with an energy storage system that can temporarily raise output to 500 MWe.
Funding and cost disclosures
On 2 December 2025 the US Department of Energy selected TVA and Holtec for 400 million dollars each under its Generation III+ Small Modular Reactor Program: TVA for a BWRX-300 at the Clinch River site, and Holtec for two SMR-300 reactors at the Palisades plant in Michigan. The department stated that the selections would help deliver new nuclear generation in the early 2030s. World Nuclear News reported on 23 August 2024 that TVA's Board of Directors had approved a further 150 million dollars in advanced funding to support the development of potential small modular reactors at the Clinch River site, bringing TVA's investment since the launch of its New Nuclear Program in February 2022 to 350 million dollars.
World Nuclear News reported on 30 September 2026 that TVA had not announced a construction start date and was continuing negotiations with industry partners on cost sharing. The NRC and Department of Energy documents cited in this article and the World Nuclear News reports of 23 August 2024 and 30 September 2026 contain no total cost estimate for Clinch River Unit 1.
Status of other BWRX-300 projects
In Canada, World Nuclear News reported on 4 April 2025 that the Canadian Nuclear Safety Commission (CNSC) had issued Ontario Power Generation (OPG) a licence to construct one BWRX-300 reactor at the Darlington New Nuclear Project site; the licence is valid until 31 March 2035. On 30 March 2026 the CNSC removed the first regulatory hold point, which covers installation of the reactor building foundation. OPG submitted its application for a licence to operate the unit in March 2026. According to OPG figures reported by World Nuclear News on 23 May 2025, the budget approved with Ontario's final investment decision of 8 May 2025 is 20.9 billion Canadian dollars for four units, including contingency, interest and escalation; of this total, 6.1 billion Canadian dollars is for the first unit and 1.6 billion Canadian dollars for shared infrastructure. The same report gives 2030 as the in-service year of the first unit.
In the United States, GE Vernova announced on 16 September 2026 that Blue Energy had submitted to the NRC the first part of a construction permit application for a BWRX-300 project at the Port of Victoria, Texas. Blue Energy expects to submit the remaining part in 2027, after the one calendar year of site-specific data collection required by the NRC. World Nuclear News reported that the company plans up to five BWRX-300 units with a combined 1.5 GW alongside 1 GW of gas-fired capacity, with gas-fired supply from 2028 and a transition to nuclear generation by 2031.
In Poland, Orlen Synthos Green Energy applied to the Minister of Energy for a contract for difference covering 14 BWRX-300 units at three sites, Włocławek, Stawy Monowskie near Oświęcim and Stalowa Wola, within a development plan of 26 units; the first unit is targeted at Włocławek in 2032 (World Nuclear News, 30 June 2026). In the United Kingdom, the Office for Nuclear Regulation, the Environment Agency and Natural Resources Wales completed step 2 of the generic design assessment of the BWRX-300 in December 2025. The American Nuclear Society reported on 16 December 2025 that the regulators did not identify any fundamental safety, security, safeguards or environmental protection shortfalls in the design, and that as of that date there were no plans to deploy the BWRX-300 in the United Kingdom and no sites identified. World Nuclear News reported on 2 July 2026 that a team led by SGE had submitted an application under the UK Advanced Nuclear Framework for 14 BWRX-300 units at three sites.
Small modular reactor licensing in Uzbekistan
In Uzbekistan, the Committee on Industrial, Radiation and Nuclear Safety under the Cabinet of Ministers issued the construction licence for the first RITM-200N small modular reactor unit at the nuclear plant under construction in Jizzakh region, and first concrete was poured in June 2026 (NEI Magazine, 8 June 2026). The plant comprises two VVER-1000 units and two RITM-200N units of 55 MWe each, with annual generation of about 17.2 TWh when fully operational. Enerdata reported on 8 June 2026 that Uzbekistan expects first electricity from the RITM-200N unit in late 2029 and that the two VVER-1000 units are projected to enter service in 2033 and 2035. This publication's Weekly Insight of 11 September 2026 records the same dates, 2029 for the first small modular unit and 2033 for the first large unit.